Flexible membrane liners, covers and fabrications by MPC containment

PROTECTING OUR AIR AND WATER WITH FLEXIBLE MEMBRANE
LINERS, COVERS, AND FABRICATIONS

 

PetroGard™ X (back to specifications)

Performance Specification

1.0 SCOPE
1.1

This specification establishes the requirement for a custom factory prefabricated flexible liner system utilizing the latest state-of-the-art concepts for secondary containment in accordance with the latest Federal and Local regulations.

1.2

The work shall include design, factory fabrication, field interface assembly, anchorage hardware, piping, prefabricated interface ports, test wells, and monitoring wells.

1.3

The materials of construction shall be compatible with the product to be stored in the primary containment vessel(s), and the material's product resistance to permeability shall conform to the criteria stated elsewhere in this specification.


2.0 APPLICABLE DOCUMENTS
2.1

Specification: Federal Standard 191, material testing of protective coated industrial textiles.

2.2

Specification: A.S.T.M. Standard D751-89, method of testing coated fabrics.

2.3

Specification: MIL-I-4520, quality control inspection and testing for the fabrication of flexible membrane materials.

2.4

Specification: A.S.T.M. D-4437-84, determining the integrity of field seams used in joining flexible polymeric sheet geomembranes.

2.5

Specification: Buyers general specification and site drawings.


3.0 REQUIRED SUBMITTALS
3.1

The successful bidder shall provide material and joint test certification demonstrating that the material and fabrication joints shall comply with the physical and chemical resistance requirements of this specification.

3.2

The bid proposal shall include design drawings showing secondary containment interface details at all apertures and shall also include installation instructions.

3.3

The liner system shall be fabricated by MPC Containment Systems, Ltd., Chicago, IL.


4.0 WARRANTY
4.1

A minimum twenty year warranty covering material and workmanship is required.


5.0 ENVIRONMENTAL DESIGN REQUIREMENTS
5.1

The flexible secondary containment liner shall be capable of withstanding the following environmental installation conditions: 5.1.1. Ambient Temperature 25 - 100 Degrees F.


7.0 MATERIAL FABRICATION DETAILS
7.1

All panel joints shall be thermal automatic high pressure welded, utilizing a two inch lap-seal construction with a tolerance of +/- a quarter of an inch on the lap.

7.2

The coating formulation shall be suitable for thermal fabrication and shall also be capable of conforming to the following test procedures without affecting the requirements of Section 6.0.

7.2.1Dead Load Criteria for Joints:
7.2.1.1

Seams carry a minimum dead load of 50% of the minimum strip tensile without separation of the fabric in the warp direction when the temperature of the FML is 70 degrees F, when tested in accordance with MIL-T-52983E.

7.2.1.2

Seams carry a minimum dead load of 25% of the strip tensile when the temperature of the FML is 160 degrees F, when tested in accordance with MIL-T-52983E.

7.2.1.3

Seams shall carry a minimum seam shear strength of 95% of the minimum strip tensile strength of the fabric when tested in accordance with A.S.T.M. D-751, Section 50.

7.3

Patterning

7.3.1

The flexible membrane liner shall be fabricated from full length modular panels with a maximum of one horizontal splice seam per panel. Splice seams shall be used only when required to utilize full roll size.

7.3.2

Panel joints shall be patterned as shown on the drawings.

7.3.3

Secondary joints and reinforcing areas shall be thermally welded. Stitching and cementing shall not be allowed for normal panel fabrication.

7.3.4

Aperture locations located in the liner shall be suitably reinforced as common practice by the factory fabricator.
Aperture locations in general shall be produced from rigid bulkhead fittings and other mechanical compression members made from synthetic type materials which normally resist corrosion.


8.0 ANCHORAGE SYSTEM
8.1

The liner shall be provided with an anchorage system which shall include hardware as detailed in the manufacturer's installation drawing.

6.0 MATERIALS AND WORKMANSHIP
6.1

Flexible Liner Material Description

6.1.1

The flexible liner material shall consist of a high strength reinforcing fabric weighing approximately thirteen (13) ounces per square yard, coated with an overall protective urethane aromatic resistance polymer; total weight is approximately thirty-eight (38) ounces per square yard.
Color: Tan.

6.1.2

Coated Liner Material. The coating compound shall be selected to have characteristics suitable for high temperature thermal-welding, shall be compounded to withstand the attack of high temperature, humidity and mildew, while at the same time, resisting the attack of the products to be stored in the primary containment vessel(s).

6.1.3

Weight and Thickness: 38 ounces per square yard + / - 2 ounces; 40 mils. + / - 2 mils.

6.1.4

Tensils Strength
Grab lbs.,A.S.T.M.,D-751     1,100 Ibs/1,100 Ibs.
1" strip lbs.,A.S.T.M.,D-751 775 Ibs/725 Ibs.

6.1.5

Hydrostatic Resistence:
Fed. Std. 5512.1                                  600 psi

6.1.6

Adhesion per one inch of width
A.S.T.M. D-751 (2" per minute)            20lbs

6.1.7

Low Temperature:
A.S.T.M. D-2136.                                        -50°

6.1.8

Flexibility/Resistance to Cracking:     PASS
Lab Procedure: Ten (10) pound weighted roller, sample size 2" x 12", fold 180 Degrees, pass roller ten times:         PASS

6.1.9

Chemical Resistance: The liner material shall meet the following test criteria for automotive fuels:

Test Procedure: : Permeability A.S.T.M. E-96
Procedure BW
Requirement:
Reference Fuel B .05 oz/Sq Ft/24 hrs.
6.1.10

Bursting Strength:
A.S.T.M. D-751,
Section 18.2                                     1750 lbs.


9.0 INSTALLATION
9.1

Installation of the factory manufactured liner system shall be performed by a factory approved and certified contractor.

9.2

A contractor who is not trained or certified may install the secondary containment liner system only under the direction of the factory authorized field technical assistance supervisor. Under this condition, the factory will provide a field report to the construction manager that the liner was installed under his direction.

9.3

The manufacturer of the secondary containment system shall supply detailed installation drawings covering all components supplied.


10.0 TESTING OF THE SECONDARY CONTAINMENT
          LINER SYSTEM

10.1

The liner manufacturer shall provide written certification that the liner has. been vacuum box tested at all panel thermal welded joint locations, and all panel materials have been visually inspected with defects noted and corrected prior to packaging. (Testing per A.S.T.M. D-4437 Mod. 1-2 PSI max.)

10.2

When a membrane liner is fabricated, seamed, sealed, modified or repaired in the field, the part so fabricated, seamed, sealed, modified or repaired shall be subjected to a performance test prescribed by the manufacturer.





PETROGARD  X

CHEMICAL COMPATIBILITY CHART


ASTM FUEL B HYDRAULIC FLUID
ASTM FUEL CJP-4
AVIATION GASJP-5
CRUDE OILKEROSENE
DIESEL FUELMETHANOL
ETHANOLMINERAL SPIRITS
FUEL OILMTBE
GASOLINE, LEADEDNAPTHA
GASOLINE, PREMIUM UNLEADED PETROLEUM HEAVY CAT CRACK
GASOLINE, REGULAR UNLEADEDPETROLEUM 95 OCTANE REFORMATE


The data shown is the result of the following laboratory tests and is intended to serve only as a guide:

Permeability ASTM E-96
Solubility & Swell ASTM D-543
Tensile & Elongation ASTM D-751


Results were arrived at by visual and physical examination in the test fluid for 7 days at room temperature. Results represent the ability of the material to retain its performance properties. When considering PetroGard IX for a specific application, it is important to study other requirements such as permeability, service temperature, concentration, size to be contained, etc. MPC Containment Systems, Ltd. Technical Department should be consulted for further recommendations. This table is presented and accepted at users risk.

We believe that the above information is the best currently available on the subject. It is offered as a possible helpful suggestion in experimentation you may care to undertake along these lines. It is subject to revision as additional knowledge and experience are gained.

GO TO TOP

 Sitemap | Privacy Policy

800-621-0146
4834 S. Oakley, Chicago, Illinois 60609-4036 phone 773-927-4120 fax 773-650-6028
info@mpccontainment.com