| As a part of
a new tank construction, MPC fabricates and attaches
a PetroGard VI flexible
membrane
tank bottom inside the concrete ring wall, then installs
cathodic protection as required.
Repairing an existing tank involves laying
a flexible membrane liner over the old steel floor,
attaching it with carbon steel anchorage hardware to
studs which have been welded to the tank wall. After
covering the API650 tank bottom with sand and installing
cathodic protection, a new steel floor is welded in
place.
|